Problem 5 (2004 AIME II)
Understand the scale
Suggest tags for this problem
This problem does not have any tags yet. Add a few useful tags and once enough people agree, they will be added here automatically.
Problem
In order to complete a large job, workers were hired, just enough to complete the job on schedule. All the workers stayed on the job while the first quarter of the work was done, so the first quarter of the work was completed on schedule. Then workers were laid off, so the second quarter of the work was completed behind schedule. Then an additional workers were laid off, so the third quarter of the work was completed still further behind schedule. Given that all workers work at the same rate, what is the minimum number of additional workers, beyond the workers still on the job at the end of the third quarter, that must be hired after three-quarters of the work has been completed so that the entire project can be completed on schedule or before?